The European Court of Auditors has predicted that the costs of Iter, the fusion reactor under construction in Cadarache, France, are likely to spiral after ongoing construction delays.
In a report on EU joint undertakings, the court said that Iter, which was audited in April, is running at least 30 months behind schedule. Furthermore, Iter still lacks a contractual system to minimise and punish cost overruns with contractors—something that was meant to be established after a review by the Council of Ministers in 2010.
The court said that the project’s 2010 construction budget estimate of €6.6 billion was “subject to significant risk of increase”, as the current schedule of the project was deemed unrealistic. Iter’s construction alone is expected to cost an extra €300 million, the court said in its report, issued on 24 November.